Thank you, Mr. Speaker. Mr. Speaker, the highway 3 reconstruction is broken into a number of phases. Two contracts were let out, publicly tendered, one from the far end from Rae-Edzo section towards Yellowknife.
--Laughter
Mr. Speaker, let me start again. The contract has been broken into two sections this year. It started initially in the previous year, work had begun. The contract had been broken down into two sections, one from Rae-Edzo towards Yellowknife and the other section is from Yellowknife towards Rae. They have been broken down into two sections. The far section, a multi-year contract was awarded to the team of Nishi-Khon SNC Lavilin and Pelly Construction along with Arny's Construction. They have the section there and I believe it is to cover approximately nine kilometres, in that area, and there is another four kilometres from Yellowknife towards Rae that just recently went out, and I believe that clearing has already been done on these areas and the work is to start in the very near future. Thank you, Mr. Speaker.