I am happy to hear that the Members are getting interested in some projects in the Beaufort-Delta. The department was able to resurface 26 kilometres of the Inuvik to Tuktoyaktuk Highway this summer, which utilized 15,000 square metres of aggregate. This was over and above the ongoing maintenance that we have completed by local contractors. The department has also hired a consultant to review the entirety of the Inuvik to Tuktoyaktuk Highway for any additional capital work that may be required. Infrastructure will also work to secure required funding as a result of that report. Additionally, we are working with the Department of ITI to secure funding for some highway pullouts.