Thank you, Mr. Chairman. Yes, we are very sensitive to this piling issue. Pilings should come from the NWT if they are available; I agree with that 100 per cent, and we are trying to make sure that does happen. If somehow some of it slips by us this year, guaranteed, it will not slip by us next year. We are trying to make sure the pilings come from the NWT because that leaves dollars in the North.
We have many different ways of contracting. Design, supply and erect contracts are done, and labour only where they only supply the labour, and then the NWT Housing is the project manager and supply, ship and erect. So some communities and areas prefer one or the other or a mixture of them. That is the way they get the most benefit. If your area is design built, we could look at doing that in your area on the next contracts, if that is what they want to do.