Thank you, Mr. Speaker. I would like to ask the Minister of DPW a question with regard to the construction of the academic building in Fort Smith. Mr. Speaker, it is my understanding that the tender documents for the academic buildings are being developed by Clarke Bowler and not DPW; however, DPW has the final say in awarding the contracts. Mr. Speaker, the last tender was combined, after it initially went out as a single tender. So, in fact, there were two tenders for the same project.
Jeannie Marie-Jewell on Question 57-12(7): Method Used In Awarding Tenders
In the Legislative Assembly on February 15th, 1995. See this statement in context.
Question 57-12(7): Method Used In Awarding Tenders
Item 6: Oral Questions
February 14th, 1995
Page 107
Jeannie Marie-Jewell Thebacha
See context to find out what was said next.