Mr. Chairman, in the main estimate books, the Highway No. 3 kilometre 0 to 154 for $4,541,000, that should be 18 kilometres of highway for that amount. For the other, the third one down, Highway 3 (b) kilometre 154 to 243 at $3,410,000, that is approximately 12 kilometres of road. Thank you.
Jim Antoine on Committee Motion 14-13(4): Recommendation To Reinstate Original Funding For Arviat Airport Lighting Project
In the Legislative Assembly on February 18th, 1997. See this statement in context.
Committee Motion 14-13(4): Recommendation To Reinstate Original Funding For Arviat Airport Lighting Project
Item 19: Consideration In Committee Of The Whole Of Bills And Other Matters
February 17th, 1997
Page 676