Thank you, Mr. Speaker. In a briefing that was held last night regarding the Government Operations Committee, I do have copies of a document in a presentation by the people who are heading up the P3 Initiative, it clearly states that the project has been deferred for a year. Could the Minister check with the department that is heading up the P3 Initiative along with her department and the community to clarify this issue because it states that it has been deferred and will be implemented a year from now? Can you clarify that for me, please?
David Krutko on Question 579-13(5): Deferral Of Fort Mcpherson Water Supply Project
In the Legislative Assembly on May 29th, 1998. See this statement in context.
Supplementary To Question 579-13(5): Deferral Of Fort Mcpherson Water Supply Project
Question 579-13(5): Deferral Of Fort Mcpherson Water Supply Project
Item 6: Oral Questions
May 28th, 1998
Page 1484
See context to find out what was said next.