Mr. Chairman, that is correct. The total amount for building the winter road is $195,000. This $101,000 plus the $94,000 we mentioned yesterday that is coming from other sources. How much we actually have to put in, that is the maximum. The amount we actually have to put in is going to be dependent on our success in negotiating with the oil and gas company. Thank you.
Joe Handley on Committee Motion 38-14(3): To Defer Item "system And Communications" Under The Department Of Public Works And Services, Capital Investment Expenditures, Supplementary Appropriation No. 1, 2000-2001
In the Legislative Assembly on November 16th, 2000. See this statement in context.
Committee Motion 38-14(3): To Defer Item "system And Communications" Under The Department Of Public Works And Services, Capital Investment Expenditures, Supplementary Appropriation No. 1, 2000-2001
Item 19: Consideration In Committee Of The Whole Of Bills And Other Matters
November 16th, 2000
Page 971
See context to find out what was said next.