Thank you, Mr. Chairman. Mr. Chairman, with this particular item here, I understand what the honourable Member is saying, that Deline is only accessible by winter road and perhaps we could wait until after the interim appropriation. I think that was the suggestion.
However, it is a contract that we have to put out and it is going to have to be built to specifications. Sometimes it takes longer than others to build the unit. Therefore the reason for having it in the interim appropriation is that it is a contract we have to let, and the length of time it may take to build is taken into consideration. To be safe, we try to give it as much lead time as possible. That is the reason why it is in the interim appropriation.