Thank you, Mr. Speaker. Mr. Speaker, I have spoken to the Member a few times about this project. I will say that on May 18th, we announced the project would not be proceeding as a P3 project because it was deemed to not have met the government's requirements.
Since that time, we continue to look at ways we can ensure this project stays on schedule. I can assure the Member we are open-minded to that. We do have limited resources. We have a limited capital budget. We have these projects, and it is important that they do proceed.
Right now, I can tell you we are open. At present, the schedule, if it continues to be a government/delivered program, would be that construction would begin in the summer of 2001, with occupancy happening in the summer or fall of 2003. I think this is within the parameters that were provided to us by the proponent putting forward the P3 project.
The federal money that is going toward this project continues to be available and dedicated to this project. Thank you.