Thank you. With regard to the cost breakdown, you mentioned that the tendered costs for the construction of this facility were over budget by $300,000. Knowing that you needed an additional $300,000, why was that not looked at before the contract went out, realizing that the actual contract came in higher from what you apprised the price at? The point I am trying to make is, are we as a government underestimating the prices of these projects in the Inuvik region? By doing that, we are having to come here again and trying to get our money just to bring up that cost and realistically trying to recognize that there is an increase in costs in development in the Inuvik region, and probably in the Northwest Territories, for that matter.
As a government, is that because the planning or the design and engineering work that is going on within this government is underestimating the reality of what is out there?