Mr. Chairman, three of the individuals did most of the work on the power generation study. That study was completed at about the end of December, December 2000. In about March, it became very clear to us that there was an opportunity for us to look at our hydro potential and make that known as part of the bigger picture, what was happening across Canada and the United States. The same individuals were used.
I would have to look back at the exact dates, but roughly in March, looking at the Taltson River system and the potential that was there to have hydro provided to the south, particularly to Fort McMurray. From then on, we went on with looking at the complete picture of the hydro potential in the Northwest Territories.
So this was an extension. It was using the same individuals because of the work they had done and the expertise they have. I do not know what more I can say on that, Mr. Chairman. It was an opportunity to do it. Thank you.