Mr. Speaker, again I think we have different definitions of what a project is. Technically, the project is the way it is described in the main estimates. The project in this case is $5 million. Even though some of the contract amounts may have been moved around, the project scope is still $5 million. The timing for the whole project is still the same. It is just the contracts within the project that have been moved. It has not affected either the scope or the timing of the project, that is the $5 million. Only contracts have changed. Thank you.
Joe Handley on Question 82-14(4): Adherence To The Financial Administration Manual
In the Legislative Assembly on June 13th, 2001. See this statement in context.
Return To Question 82-14(4): Adherence To The Financial Administration Manual
Question 82-14(4): Adherence To The Financial Administration Manual
Item 6: Oral Questions