Thank you, Madam Chair. This is the estimate that has been brought forward. It breaks down for a number of things that happened and I will provide those: gymnasium wing repairs were $1.1 million, foyer replacement is estimated at $650,000, classroom wing cosmetic upgrades $500,000, and repair work to date is $250,000. The work is still ongoing on the foyer end of things, but the gymnasium was as a result of the fire that happened right on the heels of the actual collapse of the foyer.
Madam Chair, as a result of the collapse, there was some damage to the foyer entrance and the library, stuff like that, so that included that and as we got into the repairs we also had to do upgrades on other parts of the facility because of code requirement. Thank you.