Thank you, Mr. Speaker. Mr. Speaker, that's one of the reasons we have to complete this report, is because we did have some logistical problems by way of transportation, barging, looking at sites for these units, gravel was a problem in some communities, and power hookup. Because of the timing of this contract going out, we also weren't able to meet the timelines that we were looking at. So it's been moved ahead. With that, we are going to look at the overall project itself to see exactly the hiccups that we did have so we could avoid them in the future. Thank you.
David Krutko on Question 299-15(3): Review Of Market Housing Initiative
In the Legislative Assembly on October 25th, 2004. See this statement in context.
Further Return To Question 299-15(3): Review Of Market Housing Initiative
Question 299-15(3): Review Of Market Housing Initiative
Item 6: Oral Questions
October 24th, 2004
Page 964
See context to find out what was said next.