Thank you, Madam Chair. I had a question in regard to the money, the accrued interest, legal fees, bank fees. It's seeming to pile up on the Deh Cho Bridge project; it's $507,000. I'm wondering if the Minister can tell us if we're putting a timeline or a fixed date. We had the Premier mention to us this summer that we were going to put our foot down and we weren't going to be spending any more money in this area until obviously $70 million was going to fall out of the sky somehow. But when are the brakes going to be put on the spending here and when is our risk that we have there going to be stopped? Thank you.
David Ramsay on Item 19: Consideration In Committee Of The Whole Of Bills And Other Matters
In the Legislative Assembly on November 1st, 2006. See this statement in context.
Item 19: Consideration In Committee Of The Whole Of Bills And Other Matters
Item 19: Consideration In Committee Of The Whole Of Bills And Other Matters
October 31st, 2006
Page 662
See context to find out what was said next.