Thank you, Mr. Speaker. Mr. Speaker, the latest information I received, we had a contractor go up there again to thaw out the line and look at why it froze up again. As I stated last week, between the designer of the water treatment plant, Public Works and Services, and Municipal and Community Affairs, we're working on looking at what needs to be changed. The feeling is that the long piping going from the treatment plant into the water lake is probably the reason why the insulation on the piping has deteriorated, and we're putting a project together to look at replacing that whole length of line. Thank you.