Thank you, Mr. Speaker. Mr. Speaker, we did run into some problems with the project earlier on in regard to doing inspections, and finally the work wasn't done enough to par that we had to go back and basically cancel the contract, bring another contractor in to complete the work, and that's why we're a little bit behind schedule. Again, we're hoping to have the units completed. The information I had it was supposed to be completed by the 28th of February, but if it's not, I will check and get the information back to the Member. Thank you.
David Krutko on Question 473-15(4): Delays In Construction Of Senior Housing Units In Hay River
In the Legislative Assembly on February 27th, 2006. See this statement in context.
Further Return To Question 473-15(4): Delays In Construction Of Senior Housing Units In Hay River
Question 473-15(4): Delays In Construction Of Senior Housing Units In Hay River
Item 6: Oral Questions