Mr. Speaker, yes, the
contract is for the amount that the Member has indicated. It is for a price that has been signed off that includes some money towards providing and dealing with claims and, as with any large project of this size and of this nature, there is to be expected a number of claims. So far, we have received, or the project has received claims. As I indicated to the Member that raised questions about the bridge earlier, roughly $36 million has been spent to date. Of that, there is roughly a little over $3 million that has come out of the contingency fund. Thank you.