Thank you, Mr. Speaker. This question was raised yesterday. At the time I indicated that we would all agree that the best case scenario would have the project sign off the design right up front. That was not the situation. Time and capacity didn’t allow the final design as it requires very rigorous testing to be done on it. So all parties agreed that that would be done as we move forward. That is currently the situation. There has been, up to now, two reviews on the design completed. This is the final review. It is going to be done by a very competent firm that the Bridge Corporation has hired. We expect them to have the results by sometime this summer or in the fall.
Mr. Speaker, the Member is right. We have spent close to $40 million which represents just about 25 percent of the project. We are 25 percent completed. As we move forward, we expect to spend another 25 percent of the budget this coming summer. By the end of December, we expect to have 50 percent of the project done. Thank you.