The bridge project is still on budget and it’s still on schedule. We anticipate that there are going to be some delays as the review of the design required some changes.
That’s being done. We expect that to be completed and final revisions by December or January and any further changes to the contracts will be out by March. So we expect that there will be a delay of at least a half a year or more, probably that it will be one year. That shouldn’t reflect in any additional costs.
The cost that is of concern is the first payment that is going to become due in December of 2010 and that’s going to be for $2.5 million, which is the interest payment to lenders. If the bridge is not completed by June of the following year, then there will be an additional $2.5 million. So there is a good possibility that the payments will become due and there will still be no revenue being generated from the traffic that crosses the bridge. So that may be of concern and we haven’t yet calculated how we would recover those dollars. Thank you.