Thank you, Mr. Speaker. I have some more questions today for the Minister of Transportation. It gets back to the subject of the Deh Cho Bridge Project. Yesterday I had mentioned the fact that the project was sold to Members of the last government on the basis of a fixed-price contract. It was also sold to Members of the last government on the basis that benefits on
the return on investment to the Deh Cho Bridge Corporation would accrue to the community of Fort Providence. At the 11th hour the Deh Cho Bridge
Corporation didn’t have the $5 million in equity when the concession agreement was signed and in fact had to go to the contractor and another company the contractor owned, Atcon Holdings, to supplement that $5 million in equity. Now that Atcon is out of the equation, I’m just wondering what the Deh Cho Bridge Corporation is going to do to ensure that they have the $5 million in equity so that the benefits do accrue to the community of Fort Providence in the future.