Thank you, Mr. Speaker. The Member is correct; two weeks ago we were very confident that we had the makings of a deal that was going to fall within the target and goal of what we had set as a budget. Since then, there have been more negotiations with the contractor that we are talking about. In fact, I should mention that who we are negotiating with right now, today, yesterday had brought back new numbers. We have all the moving parts, as the Member has indicated, together, including lost revenue because of the delay in the construction schedule of one year, the deferral of the design, of course, and things of that nature and outstanding claims that we have to settle. It is summed up to a number, an excess of what we budgeted by $15 million. Thank you.
Michael McLeod on Question 316-16(4): Deh Cho Bridge Project
In the Legislative Assembly on February 12th, 2010. See this statement in context.
Question 316-16(4): Deh Cho Bridge Project