Mr. Speaker, in regards to the contracting process that we use, we use negotiated contracts, sole source, bidding processes, but the project that comes to mind is the project in Inuvik. I
know the original estimate when we were first looking on the books was $58 million. Then when they did basically another estimate, it came in at $79 million. The latest estimate is over $100 million. I would like to know, using the school project, is that project on cost, on time and, more importantly, can you state that there will be no cost overruns on this school project in Inuvik? Is that too soon to make that prediction? Thank you.