Thank you, Mr. Speaker. The government has identified the falls in the Snowdrift River as an ideal place for a mini-hydro development and work started in 2007-08 and there
was additional work done in 2008-09. We are also planning a large infusion this year. Hydro projects do take time and we have to collect about two years of baseline environmental data, we have to undertake the engineering work and also figure out the regulatory process that we have to go through. Once we get all of that information and develop the cost estimates and work plan, then we would have to develop a business deal with the community of Lutselk'e, and our expectation is that would have to be done within the next 12 months. Thank you, Mr. Speaker.