On a construction infrastructure project like the Deh Cho Bridge, I’m just wondering, in terms of management, construction management, corporate management, things like that, typically what would a project like that encounter in terms of a percentage of cost. If we’re looking at close to $30 million on construction management, construction overhead, to me that number seems a little bit inflated and it’s close to 15 percent of the total project costs. I’m just wondering, is that industry norm or standard or how do we explain that. Thank you.
David Ramsay on Consideration in Committee of the Whole of Bills and Other Matters
In the Legislative Assembly on February 23rd, 2010. See this statement in context.