Thank you, Mr. Chair. The Member is correct that the $15 million is added and it will bring the total project budget to $181.4 million. The breakdown of that $181.4 million is provided in one of the tables titled Deh Cho Bridge Project Estimates Summary. So in the final column it breaks down how the $181.4 million will be spent and that includes the $15 million that is being requested today.
In terms of specific interest payments, actually, the one-year delay in the project will cost additional interest of about $5.5 million. Thank you.