Typical project management related costs for a GNWT-managed project would be 10 to 15 percent, maybe 8 to 15 percent. So this is obviously on the high end of that. I’d attribute it to the structure of the project. It is a P3 project; it took us a long time to get it to where we were ready to sign the Concession Agreement. It’s got a lot of oversight on it because of the magnitude of the funding associated with it. So it’s at the high end of what you would expect. Thank you.
Russ Neudorf on Consideration in Committee of the Whole of Bills and Other Matters
In the Legislative Assembly on February 23rd, 2010. See this statement in context.