Thank you. We have tried very hard to look at all the different opportunities or any other costs to enter the project and we feel that we’ve covered all the avenues. Of course, I can’t absolutely guarantee that. We’ve also assumed full management of the project. We have a new team, we have a new contractor. Along with that, we plan to have better communications with the public as part of the responsibilities for project management. We want to have regular updates to all the MLAs and the public with the sites that they could look at, informing themselves, including establishing a website and the possibility of signage that explains some of the project information and things of that nature so the public can be more comfortable with this project and be able to have better communications all around. Thank you.
Michael McLeod on Question 402-16(4): Deh Cho Bridge Project
In the Legislative Assembly on February 25th, 2010. See this statement in context.