Thanks to the Minister. I do appreciate the commitment. That is what I’m asking for, is some kind of an approximation of costs which GNWT has had to endure for this project over and above the actual costs of the construction and the management of the project. So I am looking forward to that information.
My next question has to do with chargeback and the Minister has mentioned that many costs are charged to the project. These GNWT staff costs I presume are not charged to the project and I’d like him to confirm. I understood that the $15 million we just approved is going to be paid back to GNWT through tolls. Will these GNWT staff costs also be paid back to GNWT through tolls over time? Thank you.