Thank you, Mr. Speaker. Mr. Speaker, as I stated earlier, through the environmental review process additional information was requested. That information was gathered and supplied to the review board around alternate sites. We go from $70 million to as high as $200 million, depending on the different scenarios that we’ve looked at: across-the-lake, underwater cable and so on. Substantially more expensive than what’s in place today. Without a business case, without a customer at a kilowatt hour, there is no project unless this government itself decides to pay the additional cost for going alternate routes around the lake. Thank you.
Floyd Roland on Question 59-16(5): Taltson Hydro Expansion Project Proposed Transmission Lines
In the Legislative Assembly on March 23rd, 2010. See this statement in context.
Question 59-16(5): Taltson Hydro Expansion Project Proposed Transmission Lines
Oral Questions
March 22nd, 2010