Thank you, Mr. Chairman. I didn’t realize anybody would be looking at that level of detail. Some of the deficiencies that we have recorded are scour rock. There is also compaction that is an issue. There is also some -- I don’t know what level we want to get into -- concern over a couple of bolt holes that are now oblong that should be round. There is about a total of $4 million that are calculated for deficiencies and that is the $4 million that is being carried over. Most of the deficiencies or other deficiencies are considered to be minor.
There is some information that we’re working towards for final closure that has allowed us to not close the books or sign off until we have all the information. Some of that stuff is still coming forward from the Deh Cho Bridge Corporation. Some of the deficiencies have been dealt with. Some we are working on. Some we are just waiting for information to close them off.