Thank you, Mr. Chairman. I should point out that the issue of deficiencies is part of any project that we have on our books. All projects encounter challenges, be it big or small, there are a lot of things that are always being flagged and this project is no different. Every item that, no matter how small, if it doesn’t meet the code, if it’s not done properly, then it’s flagged and it’s either left until it’s rectified or else a solution is found to fix it. And that list changes. Some things get resolved. As the project moves forward, new issues are added to it. That will continue right until the project is completed, and even after traffic is moving on it I’m sure there will be smaller things coming forward that have to be looked at.
The time frame is something that we’ve had a lot of discussion on with the people that are going to do the actual construction. They point to November 2011. We agree that’s a date that we’d like to see traffic crossing. We have all the steel ordered. We have a new contractor that’s already on site. We have new project management that is going through a transition, and we expect to start to see some of the steel coming on to the bridge site by this summer. So we are already working quite hard to see that this project meets the deadline, I mean the time frame in place and that’s something we don’t want to see any slippage on. Thank you.