Thank you, Mr. Speaker. It’s good to see a Member consistent in these questions on the Deh Cho Bridge. The Deh Cho Bridge is proceeding very well. Over the summer months we’ve achieved our targets for the summer construction. The steel is en route and we’re expecting to start seeing the superstructure starting to be put up in the next little while.
As to the report that the Member is referencing, the draft is completed. We’re now doing a reconciliation with staff on it and we don’t anticipate there’s going to be any additional cost to the government. Thank you.