Thank you, Mr. Chair. The Member is correct; the building was just recently completed. It went through a fairly long commissioning process because there were a large number of specialized heating and mechanical systems in that building. The building was just finally turned over to us in early February by the contractor, so we achieved substantial completion. We’re now in the process of starting to move server equipment in, put cabling in and migrating the data centre functions over there. We expect to have that part of the project complete late May or early June and then the facility will be fully operational at that time. Thank you.
Paul Guy on Consideration in Committee of the Whole of Bills and Other Matters
In the Legislative Assembly on February 24th, 2011. See this statement in context.