Thank you, Mr. Speaker. The answer is yes. Right now, the challenge that we are facing is to look at the construction methods that are going to be required to provide the final completion portion of the decking including the asphalt pour and we have come to realize that there is going to be certain challenges as the weather is going to be cold at that time of the year and how do we accommodate that and how is the contractor proposing to do that. There is some technical information that has come forward that we need to review and confirm whether it is acceptable or not. That is the information that we need to, on an ongoing basis, continue to work at. Thank you.
Michael McLeod on Question 563-16(5): Auditor General’s Report On Special Audit Of The Deh Cho Bridge
In the Legislative Assembly on March 2nd, 2011. See this statement in context.
Question 563-16(5): Auditor General’s Report On Special Audit Of The Deh Cho Bridge
Oral Questions
March 1st, 2011
Deh Cho