Right now the plan is to have all information gathered by the end of August, the final decision on realignment by the month of September, and start the engineering in the same month of September and into October. We want to have our tenders out for construction sometime in October/November and we’d like to have the construction start this year, the site preparation, and the stockpiling of gravel and crushing and work on the embankment next year. We’d like to have the road opened to the travelling public by the summer of 2012 and final servicing of the road by 2013. Thank you.
Michael McLeod on Question 162-16(6): Giant Mine Remediation And Realignment Of Ingraham Trail
In the Legislative Assembly on August 19th, 2011. See this statement in context.
Question 162-16(6): Giant Mine Remediation And Realignment Of Ingraham Trail