Thank you, Mr. Speaker. It’s no secret that the Deh Cho Bridge Project has had its difficulties. It’s critical that we continue to reflect back on some of the experiences that have happened and learn from every opportunity how we can fix the mistakes and certainly not repeat them in the future. My questions today are specifically in relation to the GNWT’s relationship with the project lender who, for some reason, cut off access to the construction account sometime in February or March 2010. My questions are directed to the Minister of Finance.
Has the GNWT conducted any investigation or review into the reasons why the Deh Cho Bridge Project lenders took the unusual steps of cutting off access to the construction account in early 2010, and how might we have prevented ourselves from getting into this situation? If we have not done this, why haven’t we done this?