I’m not sure if I should thank the Minister or not, but I appreciate the answer. I am still struggling to understand. I haven’t yet heard what has changed that requires us to spend more money. We had a contract and there was a price attached to that contract. In the terms of the contract, in the parameters of the project, what has changed that now requires us to spend 10 million more dollars? Thank you.
Wendy Bisaro on Question 107-17(3): Deh Cho Bridge Project Cost Overruns
In the Legislative Assembly on June 7th, 2012. See this statement in context.
Question 107-17(3): Deh Cho Bridge Project Cost Overruns
Oral Questions
June 6th, 2012
See context to find out what was said next.