Thank you, Madam Chair. The $10 million is the additional funding that’s required for the total project costs, so that we can change the terms of the contract, so that we can help ensure that we’ll meet a fall completion date. The additional funding is going to be used to accelerate the work that’s remaining to be completed on the bridge. The contractor will hire additional workers.
He will be working 20 hours a day, and we could go longer than that, if required. The contractor is bringing additional equipment in order to get the bridge done, and additional project management help, as well, so that there is additional oversight. There is going to be a lot of moving parts on the bridge this summer, a lot of workers on the site, and we need to make sure that that is still going to happen in a safe manner and we still get good quality happening on the project. Thank you.