For the Inuvik-Tuk highway, in this fiscal year we have $3.5 million. One million was approved as part of the fall capital planning process and then a request for another $2.5 million in this supplementary appropriation. That $3.5 million will be used to carry on with the
development of the project, the various aspects of it as we continue to plan for it. A significant portion will go to complete the geotechnical work. We are into the EA process, so a number of commitments were made as part of that EA process. We have to go and collect more water information and more other hydrological information, so money will be spent on that.
Some various vegetation, wildlife and terrain analysis required for EA and also required for our design are going to be collected. Then to move forward as part of the procurement process as well, we’ll be allocating some money for that. Thank you, Madam Chair.