Thank you, Mr. Speaker. Yes, construction has started on the realignment of Highway No. 4 past Giant Mine. The work is being performed by Det’on Cho Corporation. They are in partnership with a number of local companies they have brought in to partner with them on the realignment project. Det’on Cho/Stantec, Det’on Cho/Nahanni Construction, Aboriginal Engineering, CJ Construction, Tli Cho Landtran, and also NWT Construction. They have a number of partners.
The project came within budget. The negotiations were concluded in early October. Construction is anticipated to carry on until close to Christmas time, at which time there will be a shutdown for a few months and then in the spring it will pick up again. We hope to have construction of the seven-kilometre stretch complete by November 2013.