Thank you, Mr. Speaker. In 2010 Ruskin picked up the defunct contract on the Deh Cho Bridge and took the price from $167 million to $182 million. In less than a year we needed an additional $10 million that pushed the contract to
$192 million. In the spring of 2012, the McLeod government went even further by demanding $10 million that brought the project up to $202 million.
The question is to the Minister of Transportation. What value and services did the taxpayer of the Northwest Territories receive over and above the original 2010 signed contract with the GNWT and Ruskin? In essence, did we get anything more than a bumper sticker that said open 2012 instead of 2013? Thank you.