Thank you, Madam Chair. Yes, we have gravel sources identified for the construction of the highway. Last winter we had gone and done quite a significant investigation and found the material required to construct the subgrade. We would like to carry that on to drill holes, do some more geotechnical investigation for some additional sources that are on the remainder of the route. With that information we will be able to go and finalize the design, so take it from an 85 percent to a 100 percent design. The geotechnical will also let us investigate bridge locations so we can finalize the design on the bridges as well.
Russ Neudorf on Consideration in Committee of the Whole of Bills and Other Matters
In the Legislative Assembly on March 11th, 2013. See this statement in context.