Mr. Speaker, the answer is yes. We have already taken those steps, lessons learned from the demolition of the Samuel Hearne. We have the original contractor who did the Hazmat assessment of SAMS was the same one who did Samuel Hearne. Since we got back the information on Samuel Hearne, we have actually gone and got a secondary Hazmat assessment done. But in the contracting of this next school and any future projects, we will provide a complete up-to-date Hazmat. We are also going to require contractors who wish to submit to go through the school or go through the area that we are going to do a demolition on and do their own assessment so they can put in a fair and accurate price. We will be looking more on a fixed price, based on an accurate Hazmat assessment. This should eliminate the need for significant change orders like we have seen in this particular contract.
Just as a note, although there have been some change orders, this project is still within the established budget. We haven’t gone over. Thank you, Mr. Speaker.