Thank you. I’m glad to hear the Minister is talking to our people. Building transmission lines is extremely expensive. ATCO, during the most recent Taltson fiasco, came up with about $750,000 per kilometre. Now we’re talking about building grids to the South at that rate. So that puts us in the many millions of dollars, in addition to our 30 cent kilowatt hour of power cost, so now we add that to that cost to sell our power to the South. Clearly, that’s not about to happen.
I’d like to ask the Premier what the cost of a transmission line to the South would be. What are the estimates?