Like I indicated, we think we do have a good estimate. As the Members know, the money that we are getting from the federal government is not going to be just money given to us without us having proper estimates and so on. So before the money from the federal government starts to flow into our coffers, we have to be able to demonstrate to the federal government that we know what we’re doing and what the cost of the road is going to be. Thank you.
Tom Beaulieu on Question 29-17(5): Inuvik To Tuktoyaktuk Highway Project Costs
In the Legislative Assembly on November 7th, 2013. See this statement in context.
Question 29-17(5): Inuvik To Tuktoyaktuk Highway Project Costs
Oral Questions
November 6th, 2013
See context to find out what was said next.