Thank you. Just to close the loop on the Mackenzie Valley fibre link, as the Minister referred to, we are in the procurement process right now and we should be at a stage to get indicative pricing on the project sometime within the next few weeks, and at that time we will check in with the Standing Committee on Priorities and Planning again just to give them an update of where we are with the project. Right now the apex of the project is estimated to be between $65 and $70 million, but we’ll have a better sense of what that is sometime in mid to late March and in accordance with our policy we’ll be back in front of committee to assess whether we continue or not.
In terms of the interest expense, that is related to our short-term interest expense. If Members recall, a couple of years ago we had a top-up to our short-term borrowing limit from $175 million to $275 million and that increases us to be consistent with that increase in that limit. Thank you.