Thank you, Mr. Speaker. The original completion date for the contractor was March 31, 2015, and we are still within that date. We were a little bit ahead of schedule through last summer and were hoping to do final construction and interior finishes through January and February. Unfortunately, we had an inspection on the 25th to determine if the building was ready to be opened and there were some deficiencies identified that the contractor is currently working on. We still have until March 31st to complete those final interior finishes. The original plan was to begin moving furniture and equipment in in March with the actual opening in early summer/late spring. That is still the plan and we are still on target. I can’t confirm an official date for the opening, but I will talk to the Dehcho Health and Social Services Authority. In light of this new information, I will get a date for the Member.
Glen Abernethy on Question 743-17(5): Fort Providence Health Centre
In the Legislative Assembly on March 4th, 2015. See this statement in context.
Question 743-17(5): Fort Providence Health Centre
Oral Questions
March 3rd, 2015
Great Slave
See context to find out what was said next.