Thank you, Mr. Chair. On the Tsiigehtchic Airport, that request has been brought to the department’s attention over the past number of years. Our response is it’s an affordability issue about infrastructure and they’re just over an hour from a major airport in Inuvik.
The Aklavik Willow River Bridge, the Community Access Program has provided contributions to the community over the past several years to purchase the bridge. I think the total price is about $2 million to install it. So that will become a bit of a challenge for the community as they’re looking to move forward under the Community Access Program because that program, of course, is only $1 million a year and it serves all communities in the NWT.
The replacement of the Louis Cardinal Ferry, we continue to retrofit that ferry as needs require and inspections are done on a regular basis and it continues to meet the demands that are placed on it. Thank you.