Thank you, Mr. Chair. We had $4.5 million in capital this year. We negotiated about 50 percent of that with the Gwich’in company and we tendered the other 50 percent. The Gwich’in companies are usually quite competitive in bidding on that work as well. The tendered portion of the work did get done this year. The negotiated portion was a little late in starting, s
o probably won’t get it all
done. They ran into some wet weather and bad conditions at the
end of the year. So if there’s any
money left over or work left over then we’ll carry over that funding,
or we’ll ask the House to carry it over I
guess.
In terms of the O and M on the road, we have sufficient O and M money to take care of the road in all kinds of weather conditions. Thank you.